EATON CORPORATION

Currently performing the electrical installation for the upgrade of a 4.1 MW hydroelectric plant. The scope of work includes the installation of switchgear, power and control cables and cable tray. Additionally, we are performing the electrical controls upgrade for the DCS system.

Owner: Eaton Corp
Market: Power

City: Martinsville Va.
Project Detail : Electrical Power and Controls retrofit and upgrade for a 4.1 MW hydroelectric plant
Size: